Rancho Cañada Floodplain Restoration Project

PROJECT UPDATE, MARCH 2023

The Rancho Canada Floodplain Project is moving towards producing final designs and obtaining necessary permits for construction with a target start date for construction in 2024.  The project team is also in the process of applying for funding from several state and federal grant programs.

Permits and approvals include a Section 401 Water Quality Certification and Waste Discharge Requirement administered by the Regional Water Quality Control Board, which will also ensure that the project complies with the California Environmental Quality Act (CEQA).  In January 2023 the Park District submitted a notification to the U.S. Army Corps of Engineers, along with many supporting documents, which leads to a review under the Endangered Species Act by both the U.S. Fish and Wildlife Service and National Marine Fisheries Service. In addition to federal agency approval, the project requires an agreement with the State Department of Fish and Wildlife over changes to the river. Lastly, there are analyses and filings related to historic preservation and cultural resources. The project team does not anticipate delays with permitting due to the broad input received during the planning and design process.

The project team is applying to both federal and state grant programs to fund the nearly $25 million cost of construction. There are several promising grant programs that are focused on habitat restoration for threatened and endangered fish and amphibians,  as well as, restoring natural processes and building a more resilient watershed.  The restoration team feels this project is a perfect fit for these grant programs.

 

Rendering of project elements

Project Showing Trails Using Bridge #4

 

 

 

Rendering of project elements (including Bridge 5)

Project assuming the acquisition of Bridge #5.

 

******

 

 

Monterey Peninsula Regional Park District (District) in collaboration with numerous federal, state, and local government agencies and non-profits is beginning the process to restore migration and spawning habitat for steelhead at a new location in the Carmel River watershed. The project site is on a portion of the former Rancho Cañada Golf Club property that was conveyed to the District in 2018 by the Trust for Public Land. The site is approximately 185 acres in size and spans both banks of the Carmel River. The overall goal of the project is to restore and enhance floodplain connectivity and channel processes that will foster sustainable riparian and salmonid habitat along the Carmel River, while being compatible with current and future public access at the site.

An initial outreach meeting was held on the evening of March 9, 2022.  A recording of the meeting can be found here.

 

To receive project updates, sign up for our mailing list here.

 

Project Description 

Rancho Canada Floodplain

Monterey Peninsula Regional Park District (District) in collaboration with numerous federal, state, and local government agencies and non-profits is 

beginning the process to restore migration and spawning habitat for steelhead (Oncorhynchus mykiss) at a new location in the Carmel River watershed. The project site is on a portion of the former Rancho Cañada Golf Club property that was conveyed to the District in 2018 by the Trust for Public Land. The former golf course is approximately 185 acres in size and spans both banks of the Carmel River. The project would entail excavation of a floodplain features on about 40 acres of the site that is closest to the river and construction of a new pedestrian bridge. 

A natural floodplain is vital habitat for to the survival of salmonid fish, as it serves as a nursery and rearing area to grow and mature before returning to the ocean. Such habitat, which is flooded in the wet season and typically supports robust riparian vegetation, provides far more food for young-of-the-year fish than the main part of the river. The floodplain also provides a slow-water refuge during high flow events and can also help recharge the groundwater and reduce flooding in adjacent areas.  

The Carmel River watershed contains over one hundred stream miles of high-quality spawning grounds, but virtually no floodplain. As a result, the overall goal of the Rancho Cañada Floodplain Restoration Project is to restore and enhance floodplain connectivity and channel processes that will foster sustainable riparian and salmonid habitat along the Carmel River, while being compatible with current and future public access to park lands. The project implements the recommendations of the Steelhead Recovery Plan, issued by the National Oceanic and Atmospheric Administration’s National Marine Fisheries Service (NOAA Fisheries). The project will also strive to accommodate the existing public trails on the property and will consider other public access amenities that are compatible with habitat protection. Secondary potential benefits of the project are the enhancement of public access to the river for wildlife viewing, education, and non-motorized recreation (subject to subsequent District Planning and Policy).   

Cross section of flood plane

Illustration of inundated floodplains and fish rearing

Goals and Objectives 

In 2018, a Technical Advisory Committee (TAC), consisting of numerous federal, state, and local government stakeholders was formed in collaboration with the District, California Coastal Conservancy, and Trout Unlimited for the project. The TAC drafted a vision for the project as well as goals that were based on a review of the geomorphic, hydraulic, and biological context of the site. The main goals for the project include: restoring and enhancing floodplain and channel processes in the Carmel River (at the Rancho Cañada Unit of Palo Corona Regional Park) to foster sustainable riparian and salmonid habitat consistent with District recreational access and trail needs and restoring floodplain and floodway function, while accommodating appropriate recreational uses and ensuring that the project will not increase flood water elevations. 

 

 

Project Contacts

Katrina Harrison
McBain Associates, Applied River Sciences
Water Resources Engineer

katrina (at) mcbainassociates.com 

 

Rachel Couch
State Coastal Conservancy
Project Manager
rachel.couch (at) scc.ca.gov 

 

Jake Smith
Monterey Peninsula Regional Park District
Planning & Conservation Program Manager
jsmith (at) mprpd.org

 

To receive project updates, sign up for our mailing list here.

 

Rancho Canada Floodplain

Central Coast News

  • Coastal Conservancy Awards Grants for Coastal Access, Restoration, and Climate Resilience
    2/15/2024 – Today, the Board of the State Coastal Conservancy authorized a number of grants to restore, protect, and expand access to the California coast.  Grants approved included: A grant of an amount not to exceed $35,000,000 to The Nature Conservancy to complete permitting and implement the first phase of the Ormond Beach Restoration Public Access […] (Read more on Coastal Conservancy Awards...)
  • Coastal Stories 2024 RFP now open!
    The Coastal Stories 2024 grant program is now open! This grant program aims to support inclusivity of outdoor spaces for all Californians. The primary goal of the Coastal Stories Grant Program is to promote the representation of Black, Indigenous, People of Color (BIPOC), individuals with disabilities, immigrant communities, low-income communities, and other historically excluded groups […] (Read more on Coastal Stories 2024...)
  • Diablo Canyon Lands RFQ
    The California State Coastal Conservancy (SCC) is seeking qualifications for contractors to assist SCC and its state and local agency partners, tribes, and community groups to plan for future land conservation and public and tribal uses of the roughly 12,000-acre Diablo Canyon Lands surrounding the Diablo Canyon Power Plant in San Luis Obispo County. The […] (Read more on Diablo Canyon Lands...)
Email List Icon Image Sign up and Stay Informed!
SCC/OPC Project Viewer Photo of sea otter in the ocean Help Save Sea Otters at Tax Time